Friday, May 30, 2014

Canal dredging start date

Per Phyllis Thorpe, the latest is that the dredging will commence on Thursday orFriday of next week, June 5th or 6th.

 

Monday, May 19, 2014

Update on dredging project - start date delay

Update from Phyllis Thorpe: 
The dredging will not be starting on 5/26. The dredging will probably start about a week later. By the end of this week, I will have a new projected start date, which I will forward to you for another update posting. 
Thank you! 
Phyllis Thorpe

Tuesday, May 13, 2014

Canal dredging project update - May 13, 2014

This is the first of a series of information updates that I will be providing to theTreasure Beach property owners in regard to the canal dredging project.  These updates will be provided to Angi Bell, who will post them on the community web site, http://www.treasurebeachflorida.com.  The contractor has been constructing the dewatering site since April 28th, and he will start dredging the last week in May.  At this time, the contractor has not made any changes to his proposed order of dredging or the proposed timeline he presented at the April 22, 2014 property owners' meeting.  Please see the attached Sequence of Dredging chart, to which the contractor has added a projected start date for each portion of dredging.  You will need to have your boats moored outside the dredge path, less than 17 feet from your property line, prior to the start of dredging in your canal.  If you have a dock or other structure that extends more than 15 feet from your property line, you will also need to return the signed hold harmless agreement to me prior to the start of dredging in your canal.

 

If you would like to view the aerial photo of the canal system with the original dredge path superimposed onto it, you may find it via the following link. 

https://drive.google.com/file/d/0B9UQs8MRplf8a2RMOHVqV2M3SDg/edit?usp=sharing

The file for this aerial is extremely large, so it is very cumbersome to negotiate.  However, you are welcome to come by my office and view the hard copy of the aerial at your convenience, between 7:30 and 4:00 Mondaythru Friday.  Please remember that the revised dredge path will be 2 feet further from the property lines on each side.

 

I will provide the next update in about two weeks, or sooner, if the projected dates change.

 

Please do not hesitate to call or email me, should you have any questions.

 

Thank you very much.

 

Phyllis Thorpe, Project Manager